S-07 Case study
Fryingpan Creek Bridge
The Federal Highway Administration and the National Park Service are not Sheetshift customers and did not take part. These are public bid drawings prepared by the US Government, which carry no copyright, run through Sheetshift for transparency.
Drawings prepared by Federal Highway Administration, Western Federal Lands Highway Division. Issued by National Park Service, Mount Rainier National Park.
- sheets paired
- 15
- old sheets not re-issued
- 123
- changes found
- 106
- inside a cloud
- 22
- design changes outside every cloud found
- 43
- clouds found
- 23
Listed apart, not counted as design changes: 20 revision records, 14 designer marks, 64 plotting-noise differences.
S-07.1 The sheets
Sheet by sheet.
| Sheet | Changes found | Inside a cloud | Outside every cloud | Set aside as noise |
|---|---|---|---|---|
| A.2 — SHEET INDEXread by Sheetshift AI | 4 | 1 | 0 | 3 |
| B.1 — SUMMARY OF QUANTITIESfrom the drawing index | 11 | 0 | 9 | 21 |
| B.2 — SUMMARY OF QUANTITIESfrom the drawing index | 5 | 0 | 2 | 1 |
| B.3 — SUMMARY OF QUANTITIESfrom the drawing index | 1 | 0 | 0 | 1 |
| B.4 — SUMMARY OF QUANTITIESfrom the drawing index | 12 | 0 | 8 | 7 |
| B.5 — SUMMARY OF QUANTITIESfrom the drawing index | 7 | 0 | 5 | 2 |
| B.6 — SUMMARY OF QUANTITIESfrom the drawing index | 1 | 0 | 0 | 1 |
| D.2 — TABULATION OF QUANTITIESread by Sheetshift AI | 9 | 8 | 0 | 1 |
| D.3 — TABULATION OF QUANTITIES (SHEET 2 OF 2)read by Sheetshift AI | 4 | 2 | 0 | 5 |
| D.6 — WA NP MORA 11(1)read by Sheetshift AI | 11 | 5 | 5 | 3 |
| E.6 — SIDEWALK ARTWORK TILEfrom the drawing index | 16 | 6 | 9 | 7 |
| H.1 — WALL PROFILE / WEST ABUTMENTread by Sheetshift AI | 13 | 6 | 4 | 2 |
| S.21 — STEEL GIRDER ELEVATIONread by Sheetshift AI | 3 | 1 | 0 | 3 |
| S.22 — GIRDER DETAILS - 1from the sheet text | 6 | 4 | 1 | 4 |
| S.23 — GIRDER DETAILS - 2from the sheet text | 3 | 1 | 0 | 3 |
| H.1A — title needs confirmation | 0 | 0 | 0 | 0 |
S-07.2 The written list
What the designers wrote, against what was found.
A.2 · Plan sheet #A.2. Adds additional information to Sheet Index.
Found: 1 change
B.1 · Plan sheet #B.1 through B.6. Updates the Summary of Quantities.
Found: C-008


Values: Fairly sureCoverage: Complete
Quantities in the Plan-Profile column have been updated. Roadway excavation changed from 11037 to 10572, roadway obliteration changed from 669 to 266, and mechanically stabilized earth wall changed from blank to 4429.
- Old
- 11037 | 669 | ALL | 676
- New
- 10572 | 266 | 4429 | ALL | 671
- Roadway Excavation quantity: 11037 → 10572
- Roadway Obliteration Method 1 quantity: 669 → 266
- Mechanically Stabilized Earth Wall quantity: nothing → 4429
- Contractor Furnished MSE Wall Design quantity: ALL → nothing
- Roadway Aggregate Method 2 quantity: 676 → 671
| CUYD | 10572 | |
|---|---|---|
| (header) | · | 1103710572 |
| SQYD | · | 669266 |
| SQFT | · | ALL4429 |
| LPSM | LPSM | ALL |
| CUYD | · | 676671 |
May affect Foundations and piling: Changes to earthwork and MSE wall quantities affect site preparation and retaining structures.
Re-check: Re-check excavation volumes and MSE wall design scope.
Sheetshift AI suggests. Needs an engineer's confirmation.
D.2 · Plan sheet #D.2. Updates Table.
Found: C-078


Values: Fairly sureCoverage: Complete
The totals rows for Schedule A and Schedule B have been updated with new values written next to crossed-out old values.
- Old
- 16,606 | 3,064 | -941 | -53 | 18,660 | 18,167 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,362 | 17,723
- New
- 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701
- Schedule A Totals row: 16,606 | 3,064 | -941 | -53 | 18,660 | 18,167 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,362 | 17,723 → 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701
- Schedule B Totals row: 16,606 | 3,114 | -941 | -53 | 18,710 | 18,216 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,410 | 17,776 → 16,606 16,141 | 3,114 3,444 | -941 | -53 | 18,710 18,575 | 18,216 18,085 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,410 16,389 | 17,776 17,754
| 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| (header) | 16,60616,606 16,141 | 3,0643,064 3,394 | · | · | 18,66018,660 18,525 | 18,16718,167 18,036 | 1,3781,378 1,115 | 1,3501,350 1,502 | · | · | 2,7282,728 2,617 | 16,36216,362 16,341 | 17,72317,723 17,701 |
| 16,606 16,141 | 16,606 16,141 | 3,114 3,444 | -941 | -53 | 18,710 18,575 | 18,216 18,085 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,410 16,389 | 17,776 17,754 |
| 16,606 | 16,606removed | 3,114removed | -941removed | -53removed | 18,710removed | 18,216removed | 1,378removed | 1,350removed | 822removed | 50removed | 2,728removed | 16,410removed | 17,776removed |
May affect Foundations and piling: Earthwork quantities have changed, which may affect excavation and backfill volumes.
Re-check: excavation and backfill totals
Sheetshift AI suggests. Needs an engineer's confirmation.
D.3 · Plan sheet #D.3. Updates Table.
Found: 2 changes
D.6 · Plan sheet #D.6. Adds additional information.
Found: C-100


Values: SureCoverage: Partial
Not yet explained: “R = 35”, “L = 26”, “e = 5.8” on the new sheet; “PI 22+10”, “R = 350.” on the old sheet.
A new note has been added for the end of the MSE wall at station 20+84.
- Old
- nothing
- New
- 20+84 End MSE wall See Section H for details
- new note: nothing → 20+84 End MSE wall See Section H for details
May affect Concrete frame (columns, beams, slabs, walls): MSE wall termination details affect concrete wall construction.
Re-check: MSE wall termination details
Sheetshift AI suggests. Needs an engineer's confirmation.
E.6 · Plan sheet #E.6. Adds additional information.
Found: 14 changes
H.1 · Plan sheet #H.1. Adds additional information.
Found: C-135


Values: SureCoverage: Complete
The old note defining the start of the MSE wall at station 500+00.00 has been removed.
- Old
- "WALL 01" 500+00.00 "MAIN 01" 18+21.20, RT Begin MSE Wall
- New
- nothing
- removed note: "WALL 01" 500+00.00 "MAIN 01" 18+21.20, RT Begin MSE Wall → nothing
May affect Foundations and piling: Removes the old starting point of the MSE wall.
Re-check: Verify that the old start location is no longer used.
Sheetshift AI suggests. Needs an engineer's confirmation.
H.1A · Plan sheet #H.1A. Adds page to plans set.
Found: 1 change
S.21 · Plan sheet #S.21. through S.23 Adds additional information.
Found: C-165


Values: SureCoverage: Complete
The weld table has been updated. The minimum fillet weld sizes and thickness ranges have been revised.
- Old
- WELD TABLE
- New
- MINIMUM REQUIRED FILLET WELDS
- table title: WELD TABLE → MINIMUM REQUIRED FILLET WELDS
- row 1/2 in or less: nothing → 1/2" or Less | 3/16"
- row over 1/2 in to 3/4 in: nothing → Over 1/2" to 3/4" | 1/4"
- row 3/4 in or less: 3/4" or less | 1/4" → nothing
| THICKNESS OF THICKEST | MIN. FILLET WELD SIZES | |
|---|---|---|
| 1/2" or Less | 1/2" or Less | 3/16" |
| Over 1/2" to 3/4" | Over 1/2" to 3/4" | 1/4" |
| 3/4" or less | 3/4" or lessremoved | 1/4"removed |
May affect Structural steel and connections: Weld sizes for steel connections have changed.
Re-check: Check weld sizes on shop drawings.
Sheetshift AI suggests. Needs an engineer's confirmation.
S-07.3 Where it fell short
What this run missed or got wrong.
- 2 of 23 clouds had no change found inside. Either the designer clouded something that did not change, or Sheetshift missed it.
- 7 areas could not be lined up and are listed as not checked, so a person looks at it by eye.
- 64 more differences were set aside as probably not a design change. Nothing is deleted; a person can show them again.
- 43 of the 72 design changes sit outside every cloud Sheetshift found. Whether each is a real design change, or a cloud the designer drew that Sheetshift did not recognise, is for a person to judge from the crops below.
S-07.4 Changes
The changes, with their crops.


Values: SureCoverage: Complete
The weld table has been updated. The minimum fillet weld sizes and thickness ranges have been revised.
- Old
- WELD TABLE
- New
- MINIMUM REQUIRED FILLET WELDS
- table title: WELD TABLE → MINIMUM REQUIRED FILLET WELDS
- row 1/2 in or less: nothing → 1/2" or Less | 3/16"
- row over 1/2 in to 3/4 in: nothing → Over 1/2" to 3/4" | 1/4"
- row 3/4 in or less: 3/4" or less | 1/4" → nothing
| THICKNESS OF THICKEST | MIN. FILLET WELD SIZES | |
|---|---|---|
| 1/2" or Less | 1/2" or Less | 3/16" |
| Over 1/2" to 3/4" | Over 1/2" to 3/4" | 1/4" |
| 3/4" or less | 3/4" or lessremoved | 1/4"removed |
May affect Structural steel and connections: Weld sizes for steel connections have changed.
Re-check: Check weld sizes on shop drawings.
Sheetshift AI suggests. Needs an engineer's confirmation.


Values: Fairly sureCoverage: Complete
Quantities in the Plan-Profile column have been updated. Roadway excavation changed from 11037 to 10572, roadway obliteration changed from 669 to 266, and mechanically stabilized earth wall changed from blank to 4429.
- Old
- 11037 | 669 | ALL | 676
- New
- 10572 | 266 | 4429 | ALL | 671
- Roadway Excavation quantity: 11037 → 10572
- Roadway Obliteration Method 1 quantity: 669 → 266
- Mechanically Stabilized Earth Wall quantity: nothing → 4429
- Contractor Furnished MSE Wall Design quantity: ALL → nothing
- Roadway Aggregate Method 2 quantity: 676 → 671
| CUYD | 10572 | |
|---|---|---|
| (header) | · | 1103710572 |
| SQYD | · | 669266 |
| SQFT | · | ALL4429 |
| LPSM | LPSM | ALL |
| CUYD | · | 676671 |
May affect Foundations and piling: Changes to earthwork and MSE wall quantities affect site preparation and retaining structures.
Re-check: Re-check excavation volumes and MSE wall design scope.
Sheetshift AI suggests. Needs an engineer's confirmation.


Values: Fairly sureCoverage: Complete
The totals rows for Schedule A and Schedule B have been updated with new values written next to crossed-out old values.
- Old
- 16,606 | 3,064 | -941 | -53 | 18,660 | 18,167 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,362 | 17,723
- New
- 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701
- Schedule A Totals row: 16,606 | 3,064 | -941 | -53 | 18,660 | 18,167 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,362 | 17,723 → 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701
- Schedule B Totals row: 16,606 | 3,114 | -941 | -53 | 18,710 | 18,216 | 1,378 | 1,350 | 822 | 50 | 2,728 | 16,410 | 17,776 → 16,606 16,141 | 3,114 3,444 | -941 | -53 | 18,710 18,575 | 18,216 18,085 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,410 16,389 | 17,776 17,754
| 16,606 16,141 | 3,064 3,394 | -941 | -53 | 18,660 18,525 | 18,167 18,036 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,362 16,341 | 17,723 17,701 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| (header) | 16,60616,606 16,141 | 3,0643,064 3,394 | · | · | 18,66018,660 18,525 | 18,16718,167 18,036 | 1,3781,378 1,115 | 1,3501,350 1,502 | · | · | 2,7282,728 2,617 | 16,36216,362 16,341 | 17,72317,723 17,701 |
| 16,606 16,141 | 16,606 16,141 | 3,114 3,444 | -941 | -53 | 18,710 18,575 | 18,216 18,085 | 1,378 1,115 | 1,350 1,502 | 822 | 50 | 2,728 2,617 | 16,410 16,389 | 17,776 17,754 |
| 16,606 | 16,606removed | 3,114removed | -941removed | -53removed | 18,710removed | 18,216removed | 1,378removed | 1,350removed | 822removed | 50removed | 2,728removed | 16,410removed | 17,776removed |
May affect Foundations and piling: Earthwork quantities have changed, which may affect excavation and backfill volumes.
Re-check: excavation and backfill totals
Sheetshift AI suggests. Needs an engineer's confirmation.


Values: SureCoverage: Partial
Not yet explained: “R = 35”, “L = 26”, “e = 5.8” on the new sheet; “PI 22+10”, “R = 350.” on the old sheet.
A new note has been added for the end of the MSE wall at station 20+84.
- Old
- nothing
- New
- 20+84 End MSE wall See Section H for details
- new note: nothing → 20+84 End MSE wall See Section H for details
May affect Concrete frame (columns, beams, slabs, walls): MSE wall termination details affect concrete wall construction.
Re-check: MSE wall termination details
Sheetshift AI suggests. Needs an engineer's confirmation.


Values: SureCoverage: Complete
The old note defining the start of the MSE wall at station 500+00.00 has been removed.
- Old
- "WALL 01" 500+00.00 "MAIN 01" 18+21.20, RT Begin MSE Wall
- New
- nothing
- removed note: "WALL 01" 500+00.00 "MAIN 01" 18+21.20, RT Begin MSE Wall → nothing
May affect Foundations and piling: Removes the old starting point of the MSE wall.
Re-check: Verify that the old start location is no longer used.
Sheetshift AI suggests. Needs an engineer's confirmation.
S-13 Start
Check your next revision before your team builds it.
Upload the old and the new set. The first comparison is free, up to 30 sheet pairs.
Questions? Write to hello@sheetshift.ai